Harrison Medical Center

Project info
Architect
NBBJ Architects
Building Size
500,000 SF
Calculated Annual Electricity Savings
Calculated Annual Electricity Cost Savings
Calculated Annual Steam Savings
Electrical Engineer
Location
Silverdale, WA
MEP Engineer
AEI
Modeled Annual Electricity Savings
5,064,895 kWh/yr
Project Cost
Utlility Incentive
$1,519,469
The Silverdale Hospital set a goal of achieving an energy use index (EUI) less than 100 kBtu/sf-yr for its new 500,000 square foot acute care facility. As designed, the project is predicted to have a EUI of 98.2 kBtu/sf-yr. The project meets this ambitious target through the use of a heat recovery chiller coupled with heat recovery from exhaust air, enhanced insulation, aggressive HVAC controls, and advanced lighting design and controls.